PUBLIC WORKS DIVISION

GuangZhou Subway Line 8 Project

Source: Views: Time:2018.03.09

Guangzhou subway line 8 project. The tunneling diameter is 6.28m.The stratum materials include silty clay, slurrydy clay, sand, etc. Slurry cycling volume is 2000m³/h Two sets of MTP-1000 slurry treatment system, one set of ZTJ-120 slurrying and adjusting system and one unit of APN18SL80M filter press are employed in this project.